Venue: Council Chamber, Dunedin House, Columbia Drive; , Thornaby, Stockton-on-Tees TS17 6BJ
Contact: Scrutiny Officer, Michelle Gunn
| No. | Item |
|---|---|
|
Evacuation Procedure Minutes: The Committee noted the evacuation and housekeeping procedure.
|
|
|
Declarations of Interest Minutes: Cllr Ted Strike wished it to be recorded for transparency purposes only that on item 6, Progress Update on Affordable Housing, he owned a rental property.
|
|
|
To approve the minutes of the last meeting held on 10 November 2025 Minutes: AGREED that the minutes of the meeting held on 10th November 2025 be confirmed as a correct record and signed by the Chair.
|
|
|
Progress Update of Previously Agreed Recommendations - Burial Provision Minutes: The Assistant Director gave a verbal update on the progress of the previously agreed recommendation two and three of the review regarding securing a new site for burial provision. It was noted the outcome was dependent on being able to purchase a site from land owners and so far, had not been successful. However, the matter remained under review. An update would be taken to Cabinet when required.
The number of burial years left in the Borough’s cemeteries were being monitored, with the possibility that the burial rate was slowing. The Committee asked for a recalculation in burial years. It was noted that the number of cremations were increasing, possibly contributing to a decrease in burials. The possible provision of woodland burial was highlighted by members and would be fed back to the relevant team for consideration as part of a future update.
Overall, the update provided showed that the burial provision was on track and the next formal review would be scheduled to take place in 12 months.
AGREED that the progress update be noted and a further updated presented in 12 months.
|
|
|
Progress Update of Previously Agreed Recommendations - Affordable Housing Additional documents: Minutes: Members received a progress update on the recommendations following the action plan agreed in June, noting that five recommendations were progressing. The progress included:
The Committee requested that the next progress report be presented in the next financial year, approximately six months.
AGREED that the progress update be noted and a further update would be presented in six months.
|
|
|
Scrutiny Review of Governance of Capital Projects Additional documents:
Minutes: The Committee received a series of presentations outlining how capital projects, programmes, and interventions emerged and evolved, with a particular focus on transport, Thornaby Town Deal investment, and Ash Trees to illustrate the different types of programmes.
The Transport Capital Programme came from three main sources:
Members were presented with a case study, the Elton interchange scheme, which was identified in the adopted local plan as necessary to support housing growth in West Stockton. The Council secured £10M from the Housing Infrastructure Fund in 2018, later converted from a grant to a loan, with the funding agreement signed in late 2019. Planning permission was granted in February 2021 following public consultation. The scheme was delivered through the council’s project management processes with construction lasting approximately 18 months and affected by cost increases, utilities issues and other delivery challenges. The scheme was completed on site in December 2023, at a total cost of approximately £16m and was undergoing final safety checks with national highways.
Officers clarified that there was no net long-term cost to the Council, as repayment of the loan and further funding would be secured through development contributions as part of their planning permission.
Members questioned whether extra time for unknown factors was included the planning stages and were informed that potential delays were factored into project planning prior to delivery.
Members were also presented with the Thornaby Town Deal as a case study, which provided up to £25m of grant funding, subject to a minimum 20% local match funding. Stockton received £23.9m Members were informed that:
In response to member questions, officers confirmed that the significant match funding required at the bidding stage had been secured. Members noted that from the next year onwards, the Town Deal investment would be physically visible on the ground, reflecting ... view the full minutes text for item PLA/40/25 |
|
|
Chair's Update and Select Committee Work Programme 2025-2026 Minutes: Consideration was given to the Work Programme.
AGREED that the Work Programme be noted.
|