The Committee received a presentation from the
Assistant Director of Procurement and Governance, outlining
Stockton-on-Tees Borough Council’s procurement arrangements.
The presentation included:
- The Council used a Hybrid Model
covering Construction and ICT procurement systems and
responsibilities, and General goods and services. Service departments identified requirements, while
Procurement Service managed compliance, tendering processes and
monitoring of social value.
- Procurement processes were defined
based on level of expenditure, reflected the legal requirements
within the Procurement Act, and were set out in the contract
procedure rules within the Constitution:
- Contracts under £15,000
required demonstration of value for money, goods and services
between £15,001 and £179,087 required quotations from
four suppliers, one of which had to be a local supplier, and goods
and services above £179,087 required a formal tender process,
with contracts advertised on the governments Central Digital
Platform. Alternatively, contracts could be called off under
framework agreements.
- Construction contracts had
significantly higher thresholds, with quotations permitted up to
£1million before a full tender process was required.
Alternatively, contracts could be called off under framework
agreements.
- Framework agreements were in place
to pre-select one or more suppliers. For each framework a
procurement process had taken place and terms set during this
period, which included pricing and/or call off terms. Framework
agreements could operate with single supplier or multiple suppliers
that were ranked or where further competitions took place.
- Exceptions to following Contract
Procedure Rules were recorded.
- Officers could approve contracts up
to £500,000 under delegated powers, with contracts over
£500,000 requiring Cabinet approval. This was for the total
contract figure, e.g. if the contract was for a set amount each
year over several years. Procurement decisions were made generally
by directors and had to be recorded through Delegated Decision
Records and were subject to consultation with Finance and
Procurement Services.
- A public contract register was
maintained and available online. The Council managed 551 live
contracts at the time of the meeting and contract management was
based on risk and value, with varying levels of oversight.
It was noted that the procurement of
non-social care services was part of a transformation review to
assess how money could be saved in the process, and the findings
from this would be brought to the Committee.
The Committee questioned the quotation
threshold for construction contracts. It was explained that
construction projects were generally of a higher value, often of
£100,000 or above, and competition was still achieved through
quotations and framework agreements. However, the £1million
threshold was locally determined and could be reviewed.
The level of officer delegated decision was
also questioned, and it was noted that this had been determined by
Full Council previously and included in the Constitution.
Procurement controls, finance consultation, and delegated decision
recording still applied below the threshold.
Contracts for health and social care long-term
placements were discussed. It was noted that decisions for these
placements were considered by officer panels, chaired by senior
managers, recorded formally and regularly reviewed. These
arrangements were often rolling placements rather than traditional
fixed-term contracts and notice could be given at any point.
Members also raised examples of low value
works and projects where quality concerns had arisen.
The following further information was
requested:
- Detail and value of contracts
awarded via exceptions to contract procedure rules.
- Detail regarding the construction
quotations sought for £15,001 - £1million threshold,
including frequency and supplier participation.
- Detail of officer delegated
decisions over the previous two years below the £500,000
threshold, including number of contracts approved, total value, and
background information on how the limit was established.
- Findings from the transformation
review of procurement processes.
AGREED the information provided be noted and
information requested be sought.