The
Committee received a presentation from the review’s link
officer, the Housing Regeneration & Investment Manager. The
presentation covered:
·
SBC Duties
·
SBC DFG Policy
·
Eligible works
·
Enquiry Process
·
Application Process
·
Approvals Process
·
Grant Conditions
·
Land Charges
·
Undertaking Works
·
Local Discretion and Flexibilities
·
Government Recommendations 2018
Key issues discussed included:
- The assessment of need is carried out by the
Occupational Therapist. As part of this assessment, they would
question if the person would consider moving e.g. move to a
bungalow/ground floor flat if they have mobility
issues.
- Discussion took place regarding the mean testing
of the grant, the baseline of which had not changed since 2008, and
contributions. Some people applying might qualify for a DFG but
would not be given the full amount to cover the cost of adaptations
due to their income. Also, dependent on the adaptations needed to
be carried out, works could cost over the £30,000 limit, and
the example was given of an extension that cost £90,000. In
these cases, the person would have to contribute the remaining cost
of the works. Those that were in receipt of certain means-tested
benefits were ‘passported’ to a full grant and would
not need to contribute to adaptations up to
£30,000.
- SBC would pay the costs of adaptations to a
property outside of the Borough if it was for a child placed in
care outside of the Borough. This system was reciprocated, and it
was noted that Durham Council had paid for adaptations to a
property in the Borough where a child under their care was
living.
- The number of people on the waiting list had
increased since reporting at the previous meeting and was now at
284. The Occupational Therapist could decide if a person was fast
tracked to the top of the list due to their need following a
detailed risk assessment. People on the waiting list were sent an
income form to see if they would qualify to save them being on the
list if they did not quality. Each person on the waiting list was
contacted every three months to keep them up to date on the process
and how long it was expected to take. It was questioned if the NHS
were installing at a quicker pace to SBC to aid hospital discharge,
but the link officer was not aware of this and explained that
hospital discharge usually came through SBC’s Occupational
Therapist Team.
- SBC would only fund the minimum specification
required to meet the persons need, and would refuse anything that
was above this, however the person would be able to fund
adaptations above the basic offer themselves.
- Equipment was recovered when the person no longer
required it so that it could be reused. It was indicated in the
contract when adaptations were provided that they/the family would
need to get in contact when they were no longer needed so they
could be recovered.
- If a person broke the conditions of the grant,
for example using a different contractor to the one specified, then
SBC could ask for repayment of any funds
granted.
- When Occupational Therapists assessed the person,
they recommended adaptations that would meet their needs for the
next five years. After this time, or if their needs changed before
five years, they may be reassessed and make a further
application.
- When a person was required to contribute to works
being carried out, and they advised they could not afford the
contribution, they would be referred the Local Administrator, Five
Lamps, who would check whether they were able to secure a
mainstream loan on the open market. If they could, Five Lamps would
signpost them to these market lenders. If it was confirmed they
could not obtain a loan on the open market then they would offer
them a SBC loan. This prevented people from dropping out/cancelling
their application. The policy for these local discretions had not
been reviewed since 2017.
- Adaptations in Registered Providers properties
were discussed, and it was noted that their standard for
adaptations were higher than the basic that DFG would fund. It was
questioned if there was a register of properties that had
adaptations which people could be matched with, rather than the
Registered Providers removing these when the property became empty.
It was noted that the Director of Adults, Health & Wellbeing
was due to meet with a Housing Provider regarding the adaptations
in their properties. Members welcomed this and requested that the
Director report back to the Committee.
- Foundations provided a simple toolkit online
which advised those looking to apply for a DFG if they would be
likely to qualify. It was suggested that signposting to this
toolkit could reduce the waiting list, as those who were informed
that they would not qualify would not join the local waiting list
for an assessment. Members raised concern that people may need
assistance to complete this assessment, or be put off from
applying, however were informed that it was a simple tool to advise
if they would be likely to be approved a DFG and not the
application.
- Members questioned who assessed the quality of
the work that had been carried out and it was confirmed that the
Housing Regeneration and Investment Team would do this and sign off
the work. If there were any issues within the first 12 months the
person could contact the team who would rectify the issue, but
after this it was up to the individual to maintain
it.
- Private landlords were discussed, and it was
noted that they had to provide two quotes for any adaptations/works
which would then be reviewed by a technical officer. Following the
completion of works the officer would visit the property to check
the standard.
- It was questioned whether best practice was
shared between Local Authorities across the country, and it was
noted that SBC shared best practice with colleagues in the North
and this could be brought to the Committee.
- It was noted that in 2023/24 123 entry level
showers had been fitted by the HV&E team.
AGREED that the information be
noted.