Consideration was given to the Scope and Project Plan of the
Scrutiny Review of Disabled Facilities Grant (DFG), a mean tested
grant for up to £30,000 for adaptations to homes to make it
suitable for an individual’s needs. The overall aim of the
review was to consider how the Council could deliver the service in
the most effective and efficient way whilst still meeting
vulnerable resident’s needs, as well as exploring whether
sufficient support was being offered to enable residents to secure
a DFG.
Key contributors identified were
Stockton-on-Tees Borough Council Officers, Foundations to give
information on best practice from other Authorities, and those that
had been in receipt of a DFG.
The Committee received a background
presentation from the review’s link officer, the Housing
Regeneration & Investment Manager. The presentation
covered:
·
What is a DFG
·
Funding
·
Eligibility
·
Housing Assistance Policy
·
Process for accessing a DFG
·
Timescales
·
Government Target Timescales
·
Current Pressures
Key issues discussed included:
- Carrying out adaptations allowed individuals to
live independently and stay in their homes for longer, preventing
pressures on other council and health services.
- If the adaptations required exceed £30,000
the extra cost had to be self-funded, to assist with this the
Council had a Housing Assistance Policy which provided individuals
with various loan options.
- The waiting list for DFG was discussed, and it
was noted that there were 181 on the Housing Regeneration &
Investment waiting for approval, which was currently 12 – 24
months. Once approved, and dependent on the type of adaptation, the
works would be complete within 6-12 weeks. Officers noted that
Building Services Unit had 44 on their waiting list for entry level
showers and this would take 4-5 months to complete.
- The Council had to report their timescales for
delivering a home adaptation on an annual basis and were currently
at approximately 150 days.
- The budget for DFG was discussed and it was noted
that there had to be nil balance at the end of each financial year.
Officers explained that due to the nature of the work, some
adaptations would require payments across two financial years which
proved difficult when balancing the budget and there was a need to
have a ‘buffer’ across years.
- It was noted by the Committee that forecasting
the need for adaptations was important, and officers informed that
Foundations should be able to provide further information regarding
this.
- The customer journey was identified as a key
focus for the review. It was noted that customer satisfaction
surveys were carried out at the end of the process, which tended to
be favourable, but not during the process. It was also noted that
there were two services sending out separate
surveys.
- There had been a 10% increase in tenants of
registered providers requiring a DFG in 2023/24, which was 40% of
the overall DFG Budget.
- Members wished to examine the role of the housing
providers when their tenants required adaptations including whether
they funded renovations, what happened to the adaptation when the
tenant no longer lived in the property, and whether the types of
properties required where considered when building social
housing.
- Members requested to consider the government
recommendations for delivering DFGs in more detail in the first
instance.
AGREED that the draft scope and project plan of
the review be approved.