RESOLVED that planning application 21/2130/FUL be approved in accordance with the following conditions and s106 Heads of Terms or such other conditions or Heads of Terms as the Planning Services Manager deems necessary;
01 Time Limit
The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
02 Approved Plans
The development hereby approved shall be in accordance with the following approved plan(s);
Plan Reference Number Date Received
ASK/END/0-002 REV A 22 April 2024
ASK/END/0-002 REV A 22 April 2024
ASK/MID/0-001 REV A 22 April 2024
ASK/MID/0-002 REV A 22 April 2024
B3/0-001 REV A 22 April 2024
B3/END/0-001 REV A 22 April 2024
B3/END/0-002 REV A 22 April 2024
BAI/0-001 REV A 24 February 2025
BAI/0-002 REV A 24 February 2025
EAS/END/0-001.5A 24 February 2025
EAS/END/0-002.5A 24 February 2025
EAS/MID/0-001.5A 24 February 2025
EAS/MID/0-002.5A 24 February 2025
SITE/SG/006A 24 February 2025
CAD/0-001 REV A 22 April 2024
CAD/0-002 REV A 22 April 2024
DAL/0-001 REV A 22 April 2024
510-001 22 April 2024
510-002 22 April 2024
510-003 -1.8M 22 April 2024
510-004 - 0.45M 22 April 2024
ASK/END/0-001 REV A 22 April 2024
DAL/0-002 REV A 22 April 2024
E2.1/END/0-001.5 REV A 22 April 2024
E2.1/END/0-002.5 REV A 22 April 2024
E2.1/MID/0-001.5 REV A 22 April 2024
E2.1/MID/0-002.5 REV A 22 April 2024
FER/END/0-001 REV B 8 November 2024
FER/END/0-002 REV A 8 November 2024
HOR/0-001 REV A 22 April 2024
HOR/0-002 REV A 22 April 2024
LEY/DET/0-001 REV A 22 April 2024
LEY/DET/0-002 REV A 22 April 2024
OAK/0-001 REV A 22 April 2024
OAK/0-002 REV A 22 April 2024
RIP/ALT/0-001.5 REV A 22 April 2024
RIP/ALT/0-002.5 REV A 22 April 2024
RIP/END/0-001.5 REV A 22 April 2024
RIP/END/0-002.5 REV A 22 April 2024
SAL/END/0-002.5 REV A 22 April 2024
WEN/0-002 A 22 April 2024
5205 - 103 A 8 November 2024
5205 - 203 A 24 January 2025
5205 - 253 A 24 January 2025
5205 - NE - 460 A 8 November 2024
5205 - 200 REV C 16 January 2025
500 -005 22 April 2024
03 Walkover Survey
A maximum of three months before works commencing on site for each phase of development a suitably qualified ecologist shall undertake a checking survey to ensure that no protected species or their habitat are present on site. The results of the survey shall be submitted to and approved in writing by the Local Planning Authority and any identified additional or revised mitigation measures required shall be implemented wholly in accordance with the approved details prior to the commencement of the respective phase.
04Mitigation Measures
All ecological mitigation/ recommendation measures within Chapter 6 of the submitted contained within the submitted Ecological Impact Assessment as received by the Local Planning Authority 8 November 2024 shall be implemented throughout the development in full accordance with the advice and recommendations.
05 Bat Check ... view the full minutes text for item 40