Issue - meetings

Ref No 21/2130/FUL Site Address : Land At Harrowgate Lane, Bishopgarth, Stockton-On-Tees Application Description : Erection of 54 dwellings

Meeting: 09/09/2026 - Planning Committee (Item 40)

40 Ref No 21/2130/FUL Site Address : Land At Harrowgate Lane, Bishopgarth, Stockton-On-Tees Application Description : Erection of 54 dwellings pdf icon PDF 648 KB

Additional documents:

Minutes:

For the discussion of this item please see item 21/0249/REM.

 

A vote took place and the application was approved.

 

RESOLVED that planning application 21/2130/FUL be approved in accordance with the following conditions and s106 Heads of Terms or such other conditions or Heads of Terms as the Planning Services Manager deems necessary;

 

01 Time Limit

The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

02 Approved Plans

The development hereby approved shall be in accordance with the following approved plan(s);

 

            Plan Reference Number                             Date Received

            ASK/END/0-002 REV A                              22 April 2024

            ASK/END/0-002 REV A                              22 April 2024

            ASK/MID/0-001 REV A                               22 April 2024

            ASK/MID/0-002 REV A                               22 April 2024

            B3/0-001 REV A                                           22 April 2024 

            B3/END/0-001 REV A                                 22 April 2024

            B3/END/0-002 REV A                                 22 April 2024

            BAI/0-001 REV A                                         24 February 2025

            BAI/0-002 REV A                                         24 February 2025

            EAS/END/0-001.5A                                     24 February 2025

            EAS/END/0-002.5A                                     24 February 2025

            EAS/MID/0-001.5A                                     24 February 2025

            EAS/MID/0-002.5A                                      24 February 2025

            SITE/SG/006A                                              24 February 2025

            CAD/0-001 REV A                                       22 April 2024

            CAD/0-002 REV A                                       22 April 2024   

            DAL/0-001 REV A                                        22 April 2024 

            510-001                                                         22 April 2024

            510-002                                                         22 April 2024

            510-003 -1.8M                                              22 April 2024

            510-004 - 0.45M                                           22 April 2024       

            ASK/END/0-001 REV A                              22 April 2024

            DAL/0-002 REV A                                        22 April 2024

            E2.1/END/0-001.5 REV A                          22 April 2024

            E2.1/END/0-002.5 REV A                          22 April 2024

            E2.1/MID/0-001.5 REV A                           22 April 2024

            E2.1/MID/0-002.5 REV A                           22 April 2024    

            FER/END/0-001 REV B                              8 November 2024

            FER/END/0-002 REV A                              8 November 2024

            HOR/0-001 REV A                                       22 April 2024

            HOR/0-002 REV A                                       22 April 2024

            LEY/DET/0-001 REV A                               22 April 2024

            LEY/DET/0-002 REV A                               22 April 2024

            OAK/0-001 REV A                                       22 April 2024

            OAK/0-002 REV A                                       22 April 2024                

            RIP/ALT/0-001.5 REV A                             22 April 2024

            RIP/ALT/0-002.5 REV A                             22 April 2024

            RIP/END/0-001.5 REV A                            22 April 2024

            RIP/END/0-002.5 REV A                            22 April 2024

            SAL/END/0-002.5 REV A                           22 April 2024

            WEN/0-002 A                                                22 April 2024                                                                                        

            5205 - 103 A                                                 8 November 2024

            5205 - 203 A                                                 24 January 2025

            5205 - 253 A                                                 24 January 2025

            5205 - NE - 460 A                                        8 November 2024                                           

            5205 - 200 REV C                                       16 January 2025

            500 -005                                                        22 April 2024                                                          

           

 

03 Walkover Survey

A maximum of three months before works commencing on site for each phase of development a suitably qualified ecologist shall undertake a checking survey to ensure that no protected species or their habitat are present on site. The results of the survey shall be submitted to and approved in writing by the Local Planning Authority and any identified additional or revised mitigation measures required shall be implemented wholly in accordance with the approved details prior to the commencement of the respective phase.

 

04Mitigation Measures

All ecological mitigation/ recommendation measures within Chapter 6 of the submitted contained within the submitted Ecological Impact Assessment as received by the Local Planning Authority 8 November 2024 shall be implemented throughout the development in full accordance with the advice and recommendations. 

 

05 Bat Check  ...  view the full minutes text for item 40