Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
STOCKTON-ON-TEES BOROUGH COUNCIL
CABINET DECISION
PROFORMA
Cabinet Meeting ........................................................................ 16 November 2026
|
1. |
Title of Item/Report
|
|
|
Pride in Place Central Stockton & Portrack - Update & 10-Year Plan
|
|
2. |
Record of the Decision
|
|
|
Consideration was given to a report that updated Cabinet on the progress that had been made on the Pride in Place (PiP) Programme for Central Stockton and Portrack, including the establishment of the Neighbourhood Board, the results of the engagement programme, and the progress towards a 10-year plan for the neighbourhood.
In April 2026 Cabinet received a paper about PIP, describing the programme and the next steps for the programme. Cabinet was asked to note that significant progress had been made against this programme since then.
The programme mandated the establishment of a Neighbourhood Board (Board) and the appointment of an independent chair, and for the details of the Board, the programme of community engagement and any proposals for amending the boundary of the pride in Place Neighbourhood to be submitted to the Ministry of Housing, Communities and Local Government (MHCLG) by late July 2026.
Details of the Central Stockton and Portrack Board members would be made available on the Council’s website (Pride in Place - Stockton-on-Tees Borough Council). Following an application process Michael Poole was appointed as the independent chair.
The early stages of the resident and community engagement raised questions about the neighbourhood boundary that had been specified by MHCLG, noting that the original boundary passed through Tilery, did not include a local secondary school and the south of the neighbourhood did not have a clear and logical boundary line. The Board proposed an amendment to the neighbourhood within the submission in July 2026 and had this approved by MHCLG in August 2027. Appendix A to the report showed the approved revised boundary map with the inclusion of the full Tilery estate, North Shore Academy and more logical boundary along Yarm Lane and including Trinity Gardens.
Throughout the spring and summer, the PiP Board and Council officers, in partnership with a number of community organisations, carried out a programme of engagement with residents, community groups and businesses with an interest in the neighbourhood. This work included:
• open access drop-in sessions, • attendance at community events, • an online and paper survey • group discussions • bespoke events • sessions to capture the views of communities of interest and those with protected characteristics.
Response to the engagement was good and positively received. The programme had almost 1,000 interactions. In addition to survey and spoken responses, the programme received a number of drawings, diagrams, photos and a mural in response to the questions that were asked. The key findings of the engagement were included within the report.
The communities shared many ideas of what they believe the challenges for the area to be, and suggested projects, ideas or ways of working which they felt would contribute to addressing the challenges. Reviewing all this feedback, four clear priority areas have emerged:
• Supporting Young People to Thrive – This included suggestions for youth clubs and facilities, community hubs, mentoring, apprenticeships, training and employment opportunities, while protecting young people from exploitation and substance-related harm.
• Creating Safer Communities - through community, cohesion visible policing, CCTV, better lighting, enforcement, combined with practical support and rehabilitation for people affected by addiction and homelessness.
• Driving Economic Prosperity and Housing Growth - Through supporting local businesses and start-ups, supporting business costs, developing an enhanced evening economy, bringing vacant properties back into use.
• Enhancing quality of life through Culture, Recreation and Green Space - Through events, sport, wellbeing activities, community learning, cleaner neighbourhoods and greater use of parks and public spaces.
By 27 November 2026 the Board would submit: a) a summary of the engagement activities carried out and the findings of that work. b) a 10-year vision outlining the local community’s ambitions for the future. c) a clear plan guided by community engagement for how the Board will deliver this change over the next decade.
The Board’s work had progressed well on these documents, and they were due to be completed for sign off by the Board on 19th November 2026 before submission by the Council to MHCLG.
The vision and priorities were the key focus for the 10-year plan. The documents would reflect not only what the communities aimed to tackle but also the way that this work would progress. It sets out how the programme would work with communities to develop projects and ideas and turn these into deliverable, sustainable projects with long term impacts, rather than specifying individual projects. This was consistent with the approach being taken by other PiP neighbourhoods and had been supported by MHCLG.
The plan would set out a number of next steps, including ongoing resident engagement, community workshops based around the key themes to better understand the way the PiP programme could have the biggest impact, and a proposal to launch a small grants programme late 2026/early 2027. Focussed on addressing the key priority areas, this would enable even greater community participation in the programme, it would deliver some of the ideas that residents had already put forward. Early projects may be used to generate more feedback to shape the longer-term major funding decisions.
Following the completion of the plan and sign off by the Board, the documents would be submitted by the Council to MHCLG. The Council’s role as the accountable body was to review these documents to ensure that the programme was compliant with the requirements set out in MHCLG guidance, responsive to the views of residents and consistent with the councils financial and legal procedures. It was proposed that the Director of Regeneration and Inclusive Growth in consultation with the Deputy Leader be given delegated authority to agree and submit the plan, following its approval by the PiP Board.
MHCLG required the Board to have a clear and publicly available Terms of Reference and Code of Conduct. These documents had been approved by the Board and would be made available to view on the Councils website. These documents set out how the Board and its’ members will operate.
The Council and the Board had negotiated a Memorandum of Understanding (MoU) which sets out how the two parties would work together to deliver the programme. It sets out the Council’s role as accountable body, the services that the Council would provide to the Board and the joint decision-making processes. These documents would be subject to regular review as the programme progresses, projects are delivered and, as the Board potentially evolves to gain greater independence as MHCLG’s ambitions set out.
The extensive community engagement and conversations would be the driving theme of the programme. Following submission of the plan the Board would publicise its contents and ask the community to be part of delivering it. Workshops based around each of the themes would take place to further understand the context of the topic, where PiP funding and influence could add the most value and to start to shape projects to be delivered.
As would be set out in the 10- year plan, the Board would launch a community grants programme for the remainder of 2026/27 which would support initiatives in the four priority areas. The programme will follow similar processes to those of other community grant pots delivered by the Council.
The Chair of the Pride in Place Board (Michael Poole) was in attendance at the meeting and was given the opportunity to address Cabinet.
RESOLVED that:-
1. The vision and the 4 key priority themes for the Central Stockton and Portrack neighbourhood which have been developed by the PiP Board based upon extensive residents’ engagement be approved as the strategic framework for delivery of the Pride in Place Programme.
2. The submission of the Central Stockton and Portrack Pride in Place 10-Year Plan be approved to the Ministry of Housing, Communities and Local Government and delegate authority to the Director of Regeneration and Inclusive Growth, in consultation with the Cabinet Member for Resources and Regeneration, to finalise and submit the Plan, provided that the final version remains materially consistent with the Vision, Strategic Priorities and Programme Framework approved by Cabinet.
3. The progress that has been made by the PiP Board and the work that is planned for the next stages of the programme be noted.
4. It be noted the expenditure associated with the delivery of the Pride in Place Programme will be administered in accordance with the Council's Constitution, Financial Procedure Rules, Contract Procedure Rules, approved budgets and relevant Ministry of Housing, Communities and Local Government funding conditions.
|
|
3. |
Reasons for the Decision
|
|
|
Pride in Place (PiP) is a ‘hyper local’, community-led, government funding programme. The ethos of PiP aligns with The Stockton-on-Tees Plan and Powering Our Future programme by placing residents at the heart of the work we do, by bringing people together to build stronger, more resilient communities and to create thriving places. Cabinet are asked to endorse the vision that has emerged from community engagement, delegate authority to approve the submission of the Neighbourhood Board’s 10-year plan, and note the proposed next steps to enable the council to comply with the Ministry of Housing, Communities & Local Government (MHCLG) Programme timelines and programme governance.
|
|
4. |
Alternative Options Considered and Rejected
|
|
|
None
|
|
5. |
Declared (Cabinet Member) Conflicts of Interest
|
|
|
None
|
|
6. |
Details of any Dispensations
|
|
|
None
|
|
7. |
Date and Time by which Call In must be executed
|
|
|
Midnight, 24 November 2026
|
Proper Officer
Report author: Jane Edmends
Publication date: 16/11/2026
Date of decision: 16/11/2026
Decided at meeting: 16/11/2026 - Cabinet
Accompanying Documents: